Street List for Reconstruction & Rehabilitation

2020 Street List for Reconstruction & Rehabilitation Program
Posted on 05/19/2020
Street Programs

Road construction season has arrived! The Village Board approved a $2,898,000 contract with Builder's Paving of Hillside on April 27, 2020 for the 2020 MFT (motor fuel tax) Street Reconstruction & Rehabilitation Program.  On May 18, 2020 the contract was increased to $3,037,603.51 to extend the construction limits on Walnut Avenue up to Central Rd.  This work is being funded by the Village’s share of the State’s Motor Fuel Taxes (MFT) and General Funds for Capital Improvements. 
 
Approximately 1.99 miles of streets are designated for this program, which entails five street segments to be fully reconstructed and three street segments that will be widened and fully reconstructed. The Street Resurfacing Program, which typically involves more Village streets than Reconstruction & Rehabilitation Program, will begin mid-June.

The Village's annual Street Reconstruction and Street Rehabilitation program includes three different types of construction: reconstruction, rehabilitation and street widening. These different types of construction are further explained on the Road Construction 411 page, which also provides ongoing updates regarding the status of the road projects.

Residents living on streets slated for the Street Reconstruction & Street Rehabilitation Program should have already received a mailed letter providing general information about construction.

Residents living within the project limits will receive hand delivered notices prior to construction beginning on their street and throughout the various phases of the road project.  Furthermore, you can sign up to receive emails on last-minute updates and schedule changes for this project.

We recognize this work is disruptive to your neighborhood, therefore please take the time to review progress updates on the Street Reconstruction Program and the Street Rehabilitation Program.

Streets for Reconstruction & Rehabilitation Program: 

 Street  From  To  Construction Type
Brighton Place  S Side of Briar  Valley Ln.  Reconstruction
Brighton Court N Side of Brighton Pl.  Cul-de-sac  Reconstruction
Brighton Court S. Side of Brighton Pl. Cul-de-sac  Reconstruction
Burr Oak Drive Windsor Dr. Buffalo Grove Rd. Reconstruction
Chestnut Ave. W White Oak St Buffalo Grove Rd. Reconstruction
Cypress St. S Chestnut Ave. S Highland Ave. Reconstruction w/ widening
Greenbriar Ct. Shenandoah Dr. Cul-de-sac Reconstruction
Prindle Ave. Suffield Dr. Hintz Rd. Reconstruction
Prindle Ct. Prindle Ave. Cul-de-sac Reconstruction
Stratford Rd. Suffield Dr. Canterbury Dr. Reconstruction
Walnut Ave. W. White Oak St. Central Rd. Reconstruction w/widening