Road Construction 411

2020 MFT Street Reconstruction Construction Update

Last Updated August 25, 2020
 
Greenbrier Court – Shenandoah Drive to Cul-de-Sac
Builders Paving, Inc completed the final surface layer on July 1, 2020. 
 
Initial placement of topsoil began around the curb, driveways, and sidewalk.  This is NOT the final landscaping.  The areas disturbed by construction will be restored with topsoil and sod in later summer or early fall when conditions are favorable to sod growth.

Brighton Place (include both courts) – Briar Street to Valley Lane
Builders Paving, Inc completed the final surface layer on July 14, 2020. 
 
Initial placement of topsoil began around the curb, driveways, and sidewalk.  This is NOT the final landscaping.  The areas disturbed by construction will be restored with topsoil and sod in later summer or early fall when conditions are favorable to sod growth.

Stratford Road – Suffield Drive to Canterbury Drive
Builders Paving, Inc completed the final surface layer on July 22, 2020.  

Initial placement of topsoil began around the curb, driveways, and sidewalk.  This is NOT the final landscaping.  The areas disturbed by construction will be restored with topsoil and sod in later summer or early fall when conditions are favorable to sod growth.

Prindle Avenue (includes Prindle Court) – Suffield Drive to Hintz Road
Builders Paving, Inc completed the final surface layer on July 31, 2020.  

Initial placement of topsoil began around the curb, driveways, and sidewalk.  This is NOT the final landscaping.  The areas disturbed by construction will be restored with topsoil and sod in later summer or early fall when conditions are favorable to sod growth.

Burr Oak Drive – Windsor Drive to Buffalo Grove Road
Builders Paving, Inc completed the final surface layer on August 6, 2020.  

Initial placement of topsoil began around the curb, driveways, and sidewalk.  This is NOT the final landscaping.  The areas disturbed by construction will be restored with topsoil and sod in later summer or early fall when conditions are favorable to sod growth.

Initial placement of topsoil will be placed around the curb, driveways, and sidewalk.  This is NOT the final landscaping.  The areas disturbed by construction will be restored with topsoil and sod in later summer or early fall when conditions are favorable to sod growth.

Chestnut Avenue – White Oak Street to Cypress Street
Cypress Street – Chestnut Avenue to Highland Avenue
Builders Paving, Inc completed the final surface layer on August 19, 2020.  

Initial placement of topsoil began around the curb, driveways, and sidewalk.  This is NOT the final landscaping.  The areas disturbed by construction will be restored with topsoil and sod in later summer or early fall when conditions are favorable to sod growth.

Walnut Avenue – White Oak Street to Central Road

Builders Paving, Inc is placing the final surface layer on August 25.

Initial placement of topsoil began around the curb, driveways, and sidewalk.  This is NOT the final landscaping.  The areas disturbed by construction will be restored with topsoil and sod in later summer or early fall when conditions are favorable to sod growth.
 

Overview of 2020 Rehabilitation & Reconstruction Program

The Village's Engineering Division oversees the street rehabilitation, reconstruction, resurfacing and sidewalk construction projects. Village streets selected for reconstruction are at a stage of deterioration where the curb and gutter is no longer functioning properly, there is failure of the street's subbase and the main part of the street is in poor condition.  The Project Engineer for the Street Rehabilitation & Reconstruction Program is Briget Schwab.   If you live on a street affected by this program, please sign-up to receive email updates about the work being done on your street.

 

Street  From  To  Construction Type
Brighton Place  S Side of Briar  Valley Ln.  Reconstruction
Brighton Court N Side of Brighton Pl.  Cul-de-sac  Reconstruction
Brighton Court S. Side of Brighton Pl. Cul-de-sac  Reconstruction
Burr Oak Drive Windsor Dr. Buffalo Grove Rd. Reconstruction
Chestnut Ave. W White Oak St Buffalo Grove Rd. Reconstruction
Cypress St. S Chestnut Ave. S Highland Ave. Reconstruction w/ widening
Greenbriar Ct. Shenandoah Dr. Cul-de-sac Reconstruction
Prindle Ave. Suffield Dr. Hintz Rd. Reconstruction
Prindle Ct. Prindle Ave. Cul-de-sac Reconstruction
Stratford Rd. Suffield Dr. Canterbury Dr. Reconstruction
Walnut Ave. W. White Oak St. Central Rd. Reconstruction w/widening



Overview of Resurfacing Program

Village streets selected for the resurfacing program are in the beginning stages of deterioration. This maintenance program, which involves more streets than Rehabilitation & Reconstruction, is intended to extend the life of the street. Intermittent curb and sidewalk are removed and replaced and the street is milled and resurfaced. This project is currently out for bid. The Project Engineer for the Street Resurfacing Program is Aldair Vargas.