Construction 411

Construction Update as of September 7, 2018

This schedule is tentative and subject to change. Residents directly affected by the Street Reconstruction and Street Rehabilitation Program will receive hand delivered notification prior to construction taking place. However, last minute schedule changes will only be made via e-mail. Please sign up to receive last minute notifications.

Alleghany Drive from Kennicott Avenue to Verde Drive
Burke Drive from Cul-de-sac to Ivy Lane
Chestnut Avenue from Cedar Street to White Oak Street
Cypress Street from Ridge Avenue to Chestnut Avenue
Elizabeth Drive from Kennicott Drive to Alexandria Street
Kennicott Avenue from Algonquin Road to Harvard Avenue
South Mitchell Avenue from Cedar Street to White Oak Street
North Mitchell Avenue from Oakton Street to Clarendon Street
Raleigh Court & Shirra Court off of Raleigh Street
Valley Lane from Burke Drive to Dryden Place

Construction is substantially complete.

The landscaping subcontractor began cutting and prepping the ground for the installation of the sod on Wednesday, September 5. The landscape contractor will start on the on the streets located on the south side of town and work north over the next several weeks.
As a reminder, please mark the location of or move all sprinkler systems. Sprinkler heads are especially vulnerable and may be impacted during the cutting of the existing sod. The contractor will not be held responsible for any damage to property located within the Village right-of-way.

Watering the sod and establishing the root system is included in the cost of the contract. However, we do ask for resident cooperation so the sod will flourish. Please do not cut your new sod until the root system has been established, approximately 14 days. Please cut new sod at a high height of three inches for the season. This will help your new sod grow and stay healthy.

Brighton Place from Crabtree Drive to Suffield Drive
Crabtree Drive from Brighton Place to Windsor Drive

The final surface has tentatively been rescheduled for Tuesday, September 11. Notices will be delivered once this has been confirmed by the contractor.

Sod restoration is included as part of the contract. The landscaper is currently in town and working from the south side of town to the north.

Lillian Avenue from West of Arlington Heights Road to Highland Court
The final surface has tentatively been rescheduled for Tuesday, September 11. Notices will be delivered once this has been confirmed by the contractor.

Sod restoration is included as part of the contract. The landscaper is currently in town and working from the south side of town to the north.

Ridge Avenue from Ladd Street to 200’ to the South
Rain events during the week of September 4 cancelled all scheduled work for Ridge Avenue. The contractor has rescheduled the final grading of the new pavement area to take place the week of September 10.

Catino Street from Kaspar Avenue to Ridge Avenue
Street removal and fine grading was completed on Friday, August 31. The paving operation for the first two lifts of asphalt was scheduled for Wednesday, September 5. However, the paving operation was cancelled due to the saturated subbase from the rain events over Labor Day weekend. Additional rain during the week prevented work from continuing. Weather conditions are supposed to improve next week, and the contractor is scheduled to complete subbase repairs on Tuesday, September 11. The paving operation is dependent on approval of the subbase, but has been tentatively rescheduled for Wednesday, September 12.

Rockwell Street from Salem Avenue to Ridge Avenue
Concrete work is substantially complete. Street removal and fine grading was completed on Friday, August 31. The paving operation for the first two lifts of asphalt is scheduled for Tuesday, September 4 was cancelled due to the saturated subbase from the rain events over Labor Day weekend. Additional rain during the week prevented work from continuing. Weather conditions are supposed to improve next week, and the contractor is scheduled to complete subbase repairs on Tuesday, September 11. The paving operation is dependent on approval of the subbase, but has been tentatively rescheduled for Wednesday, September 12.

Maple Street from Salem Avenue to Ridge Avenue
Concrete work is substantially complete. Street removal and fine grading was completed on Friday, August 31. The paving operation for the first two lifts of asphalt is scheduled for Tuesday, September 4. However, due to the saturated subbase from the rain events over the weekend the contractor did not want to place the second layer of asphalt. The paving operation has been tentatively rescheduled for Wednesday, September 12.

Lincoln Lane from Fairview Street to Mayfair Road
The concrete work on the west side of Lincoln Lane is substantially complete. The remaining concrete work will be done once the drainage structures have been moved to the new curb line. Concrete removal on the east side is dependent on the drainage structure and electrical subcontractor completing all work, but has been tentatively scheduled for Tuesday, September 11.

Utility Dynamics began relocating street lights on Lincoln Lane on Friday, September 7 and are expected to be completed with this work early next week.

Asphalt driveways are also included as part of this project, but they will be repaired at a later date.

Lynden Avenue from Bristol Lane to Mayfair Lane
Concrete work is substantially complete on the north side of the street. Drainage and electrical work is complete.

The concrete on the south side of the street has been tentatively scheduled for Tuesday, September 11. Residents will receive notification once this has been confirmed with contractor.

Asphalt driveways are also included as part of this project, but they will be repaired at a later date.

Newbury Place from Banbury Road to Rockwell Street
Concrete work is substantially complete on the east side of the street. Drainage and electrical work is complete.

The concrete on the west side of the street has been tentatively scheduled for Tuesday, September 11. Residents will receive notification once this has been confirmed with contractor.

Asphalt driveways are also included as part of this project, but they will be repaired at a later date.